COSTS:

Costs of installing a UV disinfection system will be site specific.

The American Water System (AWS) which operates over 80 water treatment plants is evaluating the possibility of adding UV disinfection to its treatment process. As part of the study, estimated implementation costs are addressed. According to Arora et al. (2001) the estimated O&M costs are $22,600 a year for a 1-MGD facility up to $326,500 a year for a 100-MGD facility. An equation for estimated capital cost is derived.

Capital Cost ($) = $1,766,000 + ($86,950 / MGD) X (Plant Capacity in MGD)

Cost estimates are based on the following assumptions:

1. The reactors provide a UV dose of 40 mJ/cm2
2. The reactors are installed in the filter effluent piping or in high pressure pumping stations

Cotton et al. (2001) estimated the costs of retrofitting water systems with UV disinfection. Cost estimates were developed for flows of 0.024 – 430 MGD (0.09 – 1,628 ML/d). Cost estimates were based on the following assumptions:

1. A UV dose of 40 mJ/cm2

2. LP (Low Pressure) lamps used in systems with flows < 1 MGD (3.8 ML/d)

3. UV disinfection occurs after floc, sedimentation, and filtration and before clearwell storage

4. Three filtered water supplies: low, medium, and high quality relative to UV performance factors

A. Data came from ICR (Information Collection Rule) data base
B. Water Quality Assumptions – parameters given in the table below

Water Quality Assumptions (Cotton et al., 2001)

Parameter

High

Median

Low

UV254 –cm-1

0.014

0.032

0.07

UV transmittance-%

97

93

85

Turbidity-ntu

0.04

0.1

0.3

Alkalinity-mg/L as CaCO3

10

60

140

Hardness-mg/L as CaCO3

20

100

230

5. Interstage pumps required for systems with flows > 1 MGD (3.8 ML/d) at a cost less than 10% of capital costs; small systems had sufficient hydraulic capacity due to low head loss in small UV units

6. A separate building is needed for the UV reactors

7. Equipment redundancy assumed to be a minimum of 20% or a minimum of one redundant reactor (i.e. n + 1 concept).

8. Capital costs amortized over 20 years at 7% interest rate

9. Two UV manufacturers supplied equipment and O&M costs for small systems (<1 MGD). Four UV manufacturers supplied equipment and O&M costs for large systems. Costs used are an average of the costs provided. Manufacturer equipment costs were generally within 40% of each other

10. Engineering estimates and best judgment used for other costs

11. O&M costs included annual lamp replacement for LP and LPHO lamps, semiannual replacement of MP lamps, quarterly calibration of sensors, spare parts, cleaning chemicals, monthly cleaning for systems without automatic cleaning. O&M costs varied significantly by as much as ten fold.

The assumed power costs were $0.08/kW.hr.

Using the cost information for high, median, and low water quality, estimated capital costs for the three water qualities are presented here.

Estimated Capital Costs for Three Water Types

The components used in determining the capital costs and their contribution to each of the three water types are listed here.

Capital Cost Breakdown (Cotton et al., 2001)

Cost Component

Percentage of Total Capital Costs

Small (0.27 MGD)

Medium (11 MGD)

Large (210 MGD)

UV Equipment

52

20

13

Pumps & appurtenances

NA

10

9

Building

24

9

10

Pipes & valves

NA

4

13

Site Work

NA

10

13

Electrical & instrumentation

8

8

10

Standby power

NA

3

3

Treatability testing

NA

13

3

Engineering

NA

10

11

Contractor overhead & profit

16

6

7

Legal & financial

NA

7

8

Total capital cost

$51,000

$1,200,000

$17,000,000

There was not a significant difference in capital cost between water qualities for larger flows since UV equipment costs are a relatively small percent of total cost because of the larger costs for pumps and a new building.

Using the same cost information, the estimated O&M costs for the three water types are shown here.

Estimated O&M Costs for Three Water Types

The components used in determining the O&M costs and their contribution to each of the three water types are listed here.

O&M costs breakdown (Cotton et al., 2001)

Cost Component

Percentage to Total O&M Costs

Small (0.27 MGD)

Medium (11 MGD)

Large (210 MGD)

Power

27

52

61

Labor

30

11

7

Parts

43

37

32

Total capital cost

$2,700

$23,000

$290,000

A graph presenting the estimated total unit cost for each of the three water qualities is shown below.

Estimates for Total Unit Costs for Three Water Types

Unit costs decreased with size due to economies of scale and because costs were based on average flows; thus smaller systems need greater relative peaking capacity.

The table below summarizes the capital costs and O&M costs for small, medium, and large systems with median quality water.

Costs for Median Quality Water (Cotton et al., 2001)

System

Capital Costs

O&M

Small (0.27 MGD, 1 ML/d)

$51,000 - $60,000

$2,700 - $3,300

Medium (11 MGD, 41.6 ML/d)

$1.1 - $1.4 Million

$19,000 - $39,000

Large (210 MGD, 794.9 ML/d)

$16 - $22 Million

$170,000 - $600,000

O&M cost varied significantly between water qualities for higher flows due to additional lamps needed, labor, and chemicals for cleaning.

UV disinfection is also 40 – 80% less expensive than ozone for Cryptosporidium inactivation. However, ozone will also oxidize Fe, Mn, and organics and disinfect viruses, and multiple water quality objectives need to be considered in a site-specific cost analysis.