COSTS:
Costs of installing a UV disinfection system will be site
specific.
The American Water System (AWS) which operates over 80 water treatment
plants is evaluating the possibility of adding UV disinfection to its
treatment process. As part of the study, estimated implementation costs
are addressed. According to Arora et al. (2001) the estimated O&M
costs are $22,600 a year for a 1-MGD facility up to $326,500 a year
for a 100-MGD facility. An equation for estimated capital cost is derived.
Capital Cost ($) = $1,766,000 + ($86,950 / MGD) X (Plant Capacity
in MGD)
Cost estimates are based on the following assumptions:
1. The reactors provide a UV dose of 40 mJ/cm2
2. The reactors are installed in the filter effluent piping or in
high pressure pumping stations
Cotton et al. (2001) estimated the costs of retrofitting water systems
with UV disinfection. Cost estimates were developed for flows of 0.024
– 430 MGD (0.09 – 1,628 ML/d). Cost estimates were based
on the following assumptions:
1. A UV dose of 40 mJ/cm2
2. LP (Low Pressure) lamps used in systems with flows < 1 MGD
(3.8 ML/d)
3. UV disinfection occurs after floc, sedimentation, and filtration
and before clearwell storage
4. Three filtered water supplies: low, medium, and high quality relative
to UV performance factors
A. Data came from ICR (Information Collection Rule) data base
B. Water Quality Assumptions – parameters given in the table
below
Water Quality Assumptions (Cotton et al., 2001)
Parameter |
High |
Median |
Low |
UV254
–cm-1 |
0.014 |
0.032 |
0.07 |
UV
transmittance-% |
97 |
93 |
85 |
Turbidity-ntu |
0.04 |
0.1 |
0.3 |
Alkalinity-mg/L
as CaCO3 |
10 |
60 |
140 |
Hardness-mg/L
as CaCO3 |
20 |
100 |
230 |
5. Interstage pumps required for systems with flows > 1 MGD (3.8
ML/d) at a cost less than 10% of capital costs; small systems had
sufficient hydraulic capacity due to low head loss in small UV units
6. A separate building is needed for the UV reactors
7. Equipment redundancy assumed to be a minimum of 20% or a minimum
of one redundant reactor (i.e. n + 1 concept).
8. Capital costs amortized over 20 years at 7% interest rate
9. Two UV manufacturers supplied equipment and O&M costs for
small systems (<1 MGD). Four UV manufacturers supplied equipment
and O&M costs for large systems. Costs used are an average of
the costs provided. Manufacturer equipment costs were generally within
40% of each other
10. Engineering estimates and best judgment used for other costs
11. O&M costs included annual lamp replacement for LP and LPHO
lamps, semiannual replacement of MP lamps, quarterly calibration of
sensors, spare parts, cleaning chemicals, monthly cleaning for systems
without automatic cleaning. O&M costs varied significantly by
as much as ten fold.
The assumed power costs were $0.08/kW.hr.
Using the cost information for high, median, and low water quality,
estimated capital costs for the three water qualities are presented
here.
Estimated Capital Costs for Three Water Types
The components used in determining the capital costs and
their contribution to each of the three water types are listed here.
Capital Cost Breakdown (Cotton et al., 2001)
Cost
Component |
Percentage of Total Capital Costs |
Small (0.27 MGD) |
Medium (11 MGD) |
Large (210 MGD) |
UV Equipment |
52 |
20 |
13 |
Pumps
& appurtenances |
NA |
10 |
9 |
Building |
24 |
9 |
10 |
Pipes
& valves |
NA |
4 |
13 |
Site
Work |
NA |
10 |
13 |
Electrical
& instrumentation |
8 |
8 |
10 |
Standby
power |
NA |
3 |
3 |
Treatability
testing |
NA |
13 |
3 |
Engineering |
NA |
10 |
11 |
Contractor
overhead & profit |
16 |
6 |
7 |
Legal
& financial |
NA |
7 |
8 |
Total
capital cost |
$51,000 |
$1,200,000 |
$17,000,000 |
There was not a significant difference in capital cost
between water qualities for larger flows since UV equipment costs are
a relatively small percent of total cost because of the larger costs
for pumps and a new building.
Using the same cost information, the estimated O&M
costs for the three water types are shown here.
Estimated O&M Costs for Three Water Types
The components used in determining the O&M costs and
their contribution to each of the three water types are listed here.
O&M costs breakdown (Cotton et al., 2001)
Cost
Component |
Percentage to Total O&M Costs |
Small (0.27 MGD) |
Medium (11 MGD) |
Large (210 MGD) |
Power |
27 |
52 |
61 |
Labor |
30 |
11 |
7 |
Parts |
43 |
37 |
32 |
Total capital cost |
$2,700 |
$23,000 |
$290,000 |
A graph presenting the estimated total unit cost for each of the three
water qualities is shown below.
Estimates for Total Unit Costs for Three Water
Types
Unit costs decreased with size due to economies of scale
and because costs were based on average flows; thus smaller systems
need greater relative peaking capacity.
The table below summarizes the capital costs and O&M costs for
small, medium, and large systems with median quality water.
Costs for Median Quality Water (Cotton et al., 2001)
System |
Capital Costs |
O&M |
Small (0.27 MGD, 1 ML/d) |
$51,000 - $60,000 |
$2,700 - $3,300 |
Medium (11 MGD, 41.6 ML/d) |
$1.1 - $1.4 Million |
$19,000 - $39,000 |
Large (210 MGD, 794.9 ML/d) |
$16 - $22 Million |
$170,000 - $600,000 |
O&M cost varied significantly between water qualities for higher
flows due to additional lamps needed, labor, and chemicals for cleaning.
UV disinfection is also 40 – 80% less expensive than ozone for
Cryptosporidium inactivation. However, ozone will also oxidize
Fe, Mn, and organics and disinfect viruses, and multiple water quality
objectives need to be considered in a site-specific cost analysis.
|